Plan compliance process for underground coal mines

dc.contributor.authorAngelov, A.A.
dc.contributor.authorNaidoo, K.
dc.date.accessioned2010-11-11T13:24:56Z
dc.date.available2010-11-11T13:24:56Z
dc.date.issued2010-05
dc.description.abstractThis paper presents a unique method of monitoring the effectiveness of the planning process as well as the execution of mine plans. The method primarily determines the degree of deviation from the original mine plans by comparing actual mined areas to initially planned mining areas. The performance of mining operations is also measured by comparing actual and planned tonnages for a particular period. Once the degree of deviation from mine plans has been established the cause/s of the deviation can be determined through a simple fault tree analysis. Accurate identification of the reasons of deviation can aid the mine in selecting possible methods to correct the deviation. It is, however, beyond the scope of this paper to discuss the methods employed in correcting such deviations, as each mining operation will have unique causes of plan deviation and methods of remedying them. Deviations from the plan greatly affect the yields obtainable, which in turn affects the life of mine, thus having negative economic and financial implications. Accordingly, this paper presents a project management method which aims to reduce risk by improving planning systems to ensure optimum overall extraction of coal reserves.en_US
dc.identifier.citationAngelov, AA & Naidoo, K 2010, 'Plan compliance process for underground coal mines', Journal of the South African Institute of Mining and Metallurgy, vol. 110, no. 5, pp. 241-250. [http://www.saimm.co.za/]en_US
dc.identifier.issn0038-223X
dc.identifier.urihttp://hdl.handle.net/2263/15251
dc.language.isoenen_US
dc.publisherSouthern African Institute of Mining and Metallurgyen_US
dc.rightsSouthern African Institute of Mining and Metallurgyen_US
dc.subjectPlanning processen_US
dc.subjectExecution of mine plansen_US
dc.subject.lcshCoal mines and mining -- Planningen
dc.subject.lcshCoal mines and mining -- Managementen
dc.titlePlan compliance process for underground coal minesen_US
dc.typeArticleen_US

Files

Original bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
Angelov_Plan(2010).pdf
Size:
2.7 MB
Format:
Adobe Portable Document Format
Description:
Article

License bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
license.txt
Size:
2.43 KB
Format:
Item-specific license agreed upon to submission
Description: