Plan compliance process for underground coal mines

Show simple item record

dc.contributor.author Angelov, A.A.
dc.contributor.author Naidoo, K.
dc.date.accessioned 2010-11-11T13:24:56Z
dc.date.available 2010-11-11T13:24:56Z
dc.date.issued 2010-05
dc.description.abstract This paper presents a unique method of monitoring the effectiveness of the planning process as well as the execution of mine plans. The method primarily determines the degree of deviation from the original mine plans by comparing actual mined areas to initially planned mining areas. The performance of mining operations is also measured by comparing actual and planned tonnages for a particular period. Once the degree of deviation from mine plans has been established the cause/s of the deviation can be determined through a simple fault tree analysis. Accurate identification of the reasons of deviation can aid the mine in selecting possible methods to correct the deviation. It is, however, beyond the scope of this paper to discuss the methods employed in correcting such deviations, as each mining operation will have unique causes of plan deviation and methods of remedying them. Deviations from the plan greatly affect the yields obtainable, which in turn affects the life of mine, thus having negative economic and financial implications. Accordingly, this paper presents a project management method which aims to reduce risk by improving planning systems to ensure optimum overall extraction of coal reserves. en_US
dc.identifier.citation Angelov, AA & Naidoo, K 2010, 'Plan compliance process for underground coal mines', Journal of the South African Institute of Mining and Metallurgy, vol. 110, no. 5, pp. 241-250. [http://www.saimm.co.za/] en_US
dc.identifier.issn 0038-223X
dc.identifier.uri http://hdl.handle.net/2263/15251
dc.language.iso en en_US
dc.publisher Southern African Institute of Mining and Metallurgy en_US
dc.rights Southern African Institute of Mining and Metallurgy en_US
dc.subject Planning process en_US
dc.subject Execution of mine plans en_US
dc.subject.lcsh Coal mines and mining -- Planning en
dc.subject.lcsh Coal mines and mining -- Management en
dc.title Plan compliance process for underground coal mines en_US
dc.type Article en_US


Files in this item

This item appears in the following Collection(s)

Show simple item record